<p><P>PROBLEM TO BE SOLVED: To provide a hanging method for a cable capable of safely and economically installing a cable. <P>SOLUTION: In an overhead line 1, when a supporting cable 4 and a supported cable 5 are integrally hung by a cable hanger 6, a contributing rate of a load working on the whole hanging line is determined depending upon the magnitude of the Young's modulus and wind-receiving cross-section of each of the supporting cable 4 and the supported cable 5. The tension by the load working upon each of the cables is calculated, and the cables are hung by cable tension based on the calculated results. <P>COPYRIGHT: (C)2004,JPO</p> |