摘要 |
PROBLEM TO BE SOLVED: To provide a construction method for a concrete structure which enables a construction period to be shortened by using the minimum number of forms and the minimum amount of timbering. SOLUTION: The form 27 is supported by general timbering 46 and specific timbering 47; concrete is poured into the form 27; the general timbering 46 is removed in an imperfectly cured state before the concrete reaches design strength, so that the form 27 can be supported by the specific timbering 47; and the specific timbering 47 is removed after the concrete reaches the design strength. COPYRIGHT: (C)2004,JPO
|