发明名称 EXECUTION METHOD OF STEEL PIPE PILE
摘要 PROBLEM TO BE SOLVED: To provide an execution method of a steel pipe pile capable of effectively expecting tip bearing power and peripheral surface frictional force, and capable of shortening execution time. SOLUTION: A spiral blade 6a of an intermediate steel pipe pile 6 provided with the spiral blade 6a is buried in an intermediate part over the total length to the intermediate layer 7 having an N value of 10 to 30 by a standard penetration test, and a spiral blade 1a of a lower steel pipe pile 1 provided with the spiral blade 1a is buried only in a tip part to a lower support layer 8 having an N value of an average N value of +5 or more of the intermediate layer 7.
申请公布号 JP2003074057(A) 申请公布日期 2003.03.12
申请号 JP20010270271 申请日期 2001.09.06
申请人 ASAHI KASEI CORP 发明人 UMEDA MASAYOSHI
分类号 E02D5/56;E02D7/22;(IPC1-7):E02D7/22 主分类号 E02D5/56