摘要 |
PROBLEM TO BE SOLVED: To provide a method for smoothly executing concrete placing works in dam construction, etc. SOLUTION: The method for executing the concrete placing works in the dam construction, etc., is carried out by setting a concrete form 30 and pouring concrete inside the concrete form 30. According to the method, an attachment for rockably hanging the concrete form 30 is detachably attached to a fork claw 6 of a side-shifting-type forklift. Therefore, the concrete form 30 is hung by using the attachment attached to the forklift, and set at a predetermined location.
|