发明名称 METHOD FOR SETTING CUTOFF WALL IN SHIELD TUNNEL
摘要 PROBLEM TO BE SOLVED: To provide a method for easily setting cutoff walls in a shield tunnel construction, to thereby temporarily store rainwater in the tunnel. SOLUTION: The cutoff wall setting method is provided for temporarily storing rainwater W in the tunnel T under shield tunnel construction, which is formed of segments 1, 1, etc. According to the method, a receiving frame 5 is arranged on an inner surface of a main girder 2 of the segment 1 in a manner protruding from the main girder 2 toward the interior of the tunnel T by a predetermined length. After the receiving frame is fixed to the main girder 2, the cutoff walls 12a, 12b, 12c are set on a front surface of the receiving frame 5.
申请公布号 JP2002266600(A) 申请公布日期 2002.09.18
申请号 JP20010067911 申请日期 2001.03.12
申请人 SHIMOTORI AKIRA;KUMAGAI GUMI CO LTD 发明人 SHIMOTORI AKIRA;KIDO YOSHIKAZU;NAOZUKA KAZUHIRO;SENDAI KEIZO;SATO MAKOTO
分类号 E21F17/00;(IPC1-7):E21F17/00 主分类号 E21F17/00