发明名称 SYSTEME ET PROCEDE PERFECTIONNES D'ACCELERATION ET DE PROGRAMMATION DE FONCTIONNEMENT D'UN GROUPE ELECTROGENE A TURBINE A GAZ
摘要 <p>A gas turbine power plant is provided with an industrial gas turbine which drives a rotating brushless exciter generator coupled to a power system through a breaker. One or more of the turbine-generator plants are operated by a hybrid digital computer control system during sequenced startup, synchronizing, load, and shutdown operations. The program system for the computer and external analog circuitry operate in a multiple gas turbine control loop arrangement. Logic macro instructions are employed in programming the computer for logic operations of the control system.</p>
申请公布号 BE774179(A1) 申请公布日期 1972.04.20
申请号 BE19710774179 申请日期 1971.10.20
申请人 WESTINGHOUSE ELECTRIC CORP., GATEWAY CENTER, PITTSBURGH, PENNSYLVANIA (E.U.A.), 发明人 T.C. GIRAS;J.F. REUTHER.
分类号 H02J3/42;(IPC1-7):02P/;02C/ 主分类号 H02J3/42