发明名称 |
TRANSFORMER CONTROL DEVICE |
摘要 |
PROBLEM TO BE SOLVED: To start the operation of the optimum number of coolers at the optimum time from before a transformer is put in the state of an overload to the forecasted load on the transformer. SOLUTION: In a transformer control device which controls the the operating condition of a cooler 2 to a time fluctuating load on a transformer 1, the forecasted load on the transformer 1 and the forecasted environmental temperature of the transformer 1 are found by the mathematical model with an excess response of the transformer 1 and the time series winding mean temperature of each winding is found from the operating condition of the cooler 2 to find the time series winding mean temperature of each winding from the forecasted load and the flow rate of a cooling medium and the number of operating coolers 2 and the operation starting time of the cooler 2 are forecasted from the mathematical model so that the winding highest temperature becomes lower than a critical temperature.
|
申请公布号 |
JP2002033218(A) |
申请公布日期 |
2002.01.31 |
申请号 |
JP20000212559 |
申请日期 |
2000.07.13 |
申请人 |
MITSUBISHI ELECTRIC CORP |
发明人 |
IWABUCHI KATSUJI;OGAKI KENJI;SHINOHARA HIDEO |
分类号 |
H01F27/10;G05F1/14;H01F27/08;(IPC1-7):H01F27/10 |
主分类号 |
H01F27/10 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|