发明名称 CONSTRUCTION METHOD FOR SAND DRAIN PILE IN WATER BOTTOM GROUND
摘要 PROBLEM TO BE SOLVED: To improve a construction method for creating a sand drain pile in the water bottom ground. SOLUTION: A casing 4 for arranging water injection valves 6, 7 and 8 at proper intervals in the lengthwise direction is intruded down to the prescribed depth of the water bottom ground 2. Sand 9 equivalent to a single sand drain pile mixed with water is inputted in the casing 4. Water 10 is inputted from the water injection valves positioned in the water. After setting a water level of the water 10 in the same as a water level (a water level of a water surface 1 such as the sea and lakes and marshes) of outside water, the water is continuously discharged out of the casing 4. While maintaining the water level in the casing 4 in the state by injecting water from the water filling valves positioned in the water, the sand 9 is discharged from the lower end of the casing 4 to for the sand drain pile 11 having the prescribed length in the water bottom ground 2.
申请公布号 JP2001262556(A) 申请公布日期 2001.09.26
申请号 JP20000121748 申请日期 2000.03.21
申请人 FUDO CONSTR CO LTD 发明人 TAMURA MAMORU;MATSUYAMA HITOSHI;AZUMA SHOJI;YAMADA TAKASHI;KOSAKA YUJI
分类号 E02D3/10;(IPC1-7):E02D3/10 主分类号 E02D3/10
代理机构 代理人
主权项
地址