发明名称 JUNCTION STRUCTURE BETWEEN COLUMN AND PILE
摘要 PROBLEM TO BE SOLVED: To rationally join a column of a concrete-filled steel pipe structure to a pile. SOLUTION: In the junction structure between the column 3 of the concrete- filled steel pipe structure formed by filling concrete 2 into a steel pipe 1, and the pile 7, such as a PC pile, a cast-in-place concrete pile, a lower end 1a of the steel pipe 1 of the column 3 is installed on a pile head portion 7a of the pile 7, and the pile head portion 7a is inserted into the steel pipe 1, whereby pile main reinforcements 11 protruding from the pile head are anchored in the concrete 2 filled in the steel pipe 1. The pile head portion 7a inserted into the steel pipe 1 also functions as a column base portion of the column 3. A lower end 1a of the steel pipe 1 installed on the pile head portion 7a also functions as a shearing reinforcing member of the pile head portion 7a.
申请公布号 JP2001254365(A) 申请公布日期 2001.09.21
申请号 JP20000064016 申请日期 2000.03.08
申请人 SHIMIZU CORP 发明人 NAKAGAWA KENTARO
分类号 E02D27/00;E02D27/12;E04B1/30;E04B1/58;(IPC1-7):E02D27/00 主分类号 E02D27/00
代理机构 代理人
主权项
地址