发明名称 JOINT CONSTRUCTION BETWEEN PILE AND UPPER FRAMEWORK, AND WORKING METHOD THEREFOR
摘要 PROBLEM TO BE SOLVED: To joint a pile to an upper framework with a sufficient strength without interposing a footing. SOLUTION: The joint construction 1 between the pile and the upper framework comprises a hollow steel pipe 3 for pile installation used and left at the top of the head of pile during the formation of a cast-in-place concrete pile 2, main bar 7 of the cast-in-place concrete pile 2 extended in a hollow cylindrical space 6 for jointing surrounded by the top 5 of the pile head and the inner peripheral surface 4 of a hollow steel pipe for forming the pile, a main steel bar 9 of an RC column 8 erected inside the hollow space for jointing, an anchor 10 for fixing a brace located at a hollow space for jointing, and a concrete portion 11 poured in a hollow space for jointing in such a manner that the anchor for fixing the brace can be embedded inside a hollow space 6 jointing the anchor together with the main bars 7, 9.
申请公布号 JP2001200544(A) 申请公布日期 2001.07.27
申请号 JP20000009692 申请日期 2000.01.19
申请人 OHBAYASHI CORP 发明人 OKANO MOTOYUKI;OUCHI HAJIME
分类号 E02D5/34;E02D7/00;E02D27/12;E02D27/34;(IPC1-7):E02D27/12 主分类号 E02D5/34
代理机构 代理人
主权项
地址