发明名称 |
METHOD FOR ESTIMATING ALLOWABLE BLOWING DOWN TIME IN BLAST FURNACE |
摘要 |
PURPOSE: A method is provided to accurately estimate an allowable blowing down time which is changed according to conditions inside a blast furnace by inserting a tuyere probe into the blast furnace through a tuyere during air blowing down of a blast furnace so as to measure a temperature inside the blast furnace, and estimating a temperature variation of molten materials based on the measured temperature inside the blast furnace. CONSTITUTION: The method for estimating allowable blowing down time in a blast furnace comprises the steps of deducing the change of a temperature inside a blast furnace depending on lapse of time after stopping of air blowing by measuring the temperature inside the blast furnace in a certain time interval using a tuyere probe after blowing down (S1,S2); calculating a distance from the tuyere to molten material in the blast furnace during blowing down period (S3); calculating the surface temperature of the molten material according to the lapse of time after blowing down using the temperature change inside the furnace (S4); and estimating the time that is taken to reach to a temperature in which the molten material starts to be hardened from the change of the surface temperature of molten material as an allowable blowing down time (S5).
|
申请公布号 |
KR20010057232(A) |
申请公布日期 |
2001.07.04 |
申请号 |
KR19990059425 |
申请日期 |
1999.12.20 |
申请人 |
POHANG IRON & STEEL CO., LTD. |
发明人 |
CHO, JONG MIN;SEO, YEONG GEUN |
分类号 |
C21B9/00;(IPC1-7):C21B9/00 |
主分类号 |
C21B9/00 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|