PROBLEM TO BE SOLVED: To cope with even large and superheavy works by a manual racking system. SOLUTION: In the downstream position of the outlet conveyor 4 of a transfer press 3, flap conveyors 6 are provided, which send works 1 while portioning them out up and down. On an upper stage part in the downstream position of the flap conveyors 6, an upside intermediate conveyor 7 is arranged, and on its downstream, a payoff table 10a is installed through a transfer chute 9a. On a lower stage part in the downstream position of the flap conveyors 6, a lower side intermediate conveyor 8 is arranged, which is shorter in length than the upside intermediate conveyor 7. On the front side of the lower side intermediate conveyor 8, a rack 11 for cross-feed is provided, which is equipped with shuttle conveyors 12 moving in the left and right directions, and in front of the left and right parts of the rack 11 for cross-feed, left and right payoff tables 10b, 10c are installed through transfer chutes 9b, 9c.
|