发明名称 Building concrete roof formation method has full height cast in 2 stages to allow installation of supply pipes and lines between lower and upper cast concrete layers
摘要 The concrete roof formation method uses a shuttering provided with a lower reinforcement (2) before casting the concrete to an initial height (H1), with spacers (3) attached to the lower reinforcement for supporting an upper reinforcement projecting above this height. Installation pipes and lines (7) are laid above the cast lower concrete layer (4) before fitting the upper reinforcement (8) to the spacers and casting the upper layer of the concrete roof.
申请公布号 DE19930693(C1) 申请公布日期 2000.12.28
申请号 DE19991030693 申请日期 1999.07.05
申请人 ROLLTEC-HEIZSYSTEME PRODUKTIONS- UND VERTRIEBSGESELLSCHAFT MBH & CO. KG 发明人
分类号 E04B5/38;E04B5/48;(IPC1-7):E04B5/48;E04B5/32 主分类号 E04B5/38
代理机构 代理人
主权项
地址