发明名称 PILE CREATING CONSTRUCTION METHOD
摘要 PROBLEM TO BE SOLVED: To increase a strength of a pile and prevent the corrosion of a steel core material in the pile. SOLUTION: A pile installation ground is drilled to a specified depth, as necessary, using a casing 15 so as to form a pile installation hole (h). Next, a steel tube body 12 of tip sealed type user as a rust preventive case is inserted into the center of the pile installation hole (h), grout material (13) is filled between the steel tube body 12 and an installation hole wall (not penetrated from the hole wall into the ground), and the casing 15 is extracted. Then, a steel core material 1 is inserted from a base end opening into the steel tube body 12, and grout material 14 is filled between the outer surface of the inserted steel core material 1 and the inner surface of the steel tube body 12. A pile body is created by the hardening of these filled grout materials 13 and 14.
申请公布号 JP2000352046(A) 申请公布日期 2000.12.19
申请号 JP19990165161 申请日期 1999.06.11
申请人 RAITO KOGYO CO LTD 发明人 WADA HIROSHI;YUKI TORU;UESUGI YOSHIFUMI
分类号 E02D3/12;E02D5/30;(IPC1-7):E02D3/12 主分类号 E02D3/12
代理机构 代理人
主权项
地址