发明名称 |
GROUND IMPROVEMENT METHOD |
摘要 |
PROBLEM TO BE SOLVED: To provide a ground improvement method combined with a precast pile working method by driving precast piles into ground as a foundation for a structure and a compacted sand pile creation method for strengthening the ground by creating a number of sand piles compacted in the ground at adequate intervals, which creates no an excessively high soil strength portion and provides an excellent construction efficiency. SOLUTION: In a foundation improvement method comprising a precast pile working method in which precast piles are driven into the ground as a foundation for a structure and a compacted sand pile creating method for strengthening the ground by creating a number of compacted sand piles at adequate intervals, the sand piles 1 are driven by reducing the percentage of substitution of sand piles 1 to less than the percentage of substitution of sand piles designed when assuming that the driving of precast piles 3 to the ground 3 is none.
|
申请公布号 |
JP2000345554(A) |
申请公布日期 |
2000.12.12 |
申请号 |
JP19990160705 |
申请日期 |
1999.06.08 |
申请人 |
FUDO CONSTR CO LTD |
发明人 |
OTSUKA MAKOTO;ANDO YUTAKA;YAMAMOTO MINORU |
分类号 |
E02D5/24;E02D3/10;(IPC1-7):E02D3/10 |
主分类号 |
E02D5/24 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|