CONSTRUCTION METHOD OF UNDERGROUND STRUCTURE IN LIQUEFIED GROUND AND FOOTING CONSTRUCTION |
摘要 |
PROBLEM TO BE SOLVED: To provide footing construction of an underground structure and a construction method capable of resisting dynamic liquid pressure caused by liquefaction by only improving ground directly under the underground structure by a compaction method at a low construction cost. SOLUTION: Footing construction in a liquefied ground includes an improved ground 14 compacted from a specific depth of the ground within a range W of the bottom slab of a culvert 12 to the upper surface of a non-liquefied layer 15, earth retaining walls 11a and 11b extended from the inside of the non- liquefied layer 15 upwards of the bottom slab 12a and the culvert 12 provided in the improved ground 14 so as to bring at least the lower end of both side walls 12a and 12b into contact with the earth retaining walls 11a and 11b on both sides.
|
申请公布号 |
JP2000297441(A) |
申请公布日期 |
2000.10.24 |
申请号 |
JP19990107981 |
申请日期 |
1999.04.15 |
申请人 |
HAZAMA GUMI LTD |
发明人 |
FUNABIKI MASUO;NISHIJIMA TAKERO;ISHIGURO AKIHIKO;MIHARA MASAYA |
分类号 |
E02D3/12;E02D5/04;E02D27/34;E02D29/045;E21D13/00;(IPC1-7):E02D29/045 |
主分类号 |
E02D3/12 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|