发明名称 CONSTRUCTION CONTROL SYSTEM IN SOIL IMPROVEMENT METHOD
摘要 PROBLEM TO BE SOLVED: To efficiently and rationally control a volume of soil to be removed in a soil improvement method with earth removing. SOLUTION: In a construction control system to be applied when a soil improvement method for removing earth and sand equivalent to a grouting amount of soil improvement material is to be carried out, the detection of the depth, the number of revolutions, a penetration speed, a drawing speed and a grouting amount of soil improvement material of a screw rod is monitored, at the same time, an estimated amount of removing earth by the screw rod is calculated on the basis of the number of revolutions, and the estimated amount of the removing earth is monitored as an item of control. Then, the estimated amount of removing earth is compared with the grouting amount of soil improvement material to decide whether construction is good or not.
申请公布号 JP2000212951(A) 申请公布日期 2000.08.02
申请号 JP19990016307 申请日期 1999.01.25
申请人 FUDO CONSTR CO LTD;TENOX CORP;SHIMIZU CORP 发明人 YAMAMOTO MINORU;MIYOSHI AKIHIRO;FUKUDA ATSUO;KAMI SHUJI;KAMIMURA KAZUYOSHI;MATSUMOTO HISAYUKI
分类号 E02D3/12;(IPC1-7):E02D3/12 主分类号 E02D3/12
代理机构 代理人
主权项
地址