发明名称 |
GROUND IMPROVING METHOD APPLYING TOP-DOWN CONSTRUCTION METHOD |
摘要 |
PROBLEM TO BE SOLVED: To improve the ground just below an underground building frame into a lattice-shaped wall form mainly by sequentially repeating cutting of the ground and construction of underground building frame while constructing a main building frame to the direction of underground, and directly improving the ground just below by means of a small ground improving machine carried at a final floor finishing level, thereby constructing the final floor. SOLUTION: Cutting of the ground and construction of underground building frame constructed of beams 10 and a floor 1 are repeated sequentially downward to proceed the construction of underground part 2 of a building by the top-down construction method. The area from a lowermost floor finishing level L3 to a planned floor finishing level downward therefrom are excavated by a small backhoe or the like carried thereat, and the bottom surface of lowermost floor is 11 taken as a construction floor surface 4. For example, a one-shaft type small ground improving mechine 3 is carried onto the surface 4 from the ground. Then, the ground to be improved 5 just below the surface 4 is excavated to a specified depth D by the machine 3. Thereafter, a ground stabilizing material 7 such as cement slurry or the like is poured therein which is stirred and mixed with the excavated earth to thereby improve the ground to be improved 5.
|
申请公布号 |
JP2000160551(A) |
申请公布日期 |
2000.06.13 |
申请号 |
JP19980337073 |
申请日期 |
1998.11.27 |
申请人 |
TAKENAKA KOMUTEN CO LTD;TAKENAKA DOBOKU CO LTD |
发明人 |
SHUDO YASUHIKO;KANAO TAKEHIRO;MITSUMA AKIRA;AKIBA MASAYUKI;TAKAYANAGI KAZUTOSHI;AOKI MASAMICHI;YOSHIZAWA MUTSUHIRO;KONISHI KAZUO;FUCHIGAMI KEIICHI;UEDA KAZU |
分类号 |
E02D3/12;E02D29/045;E21D13/00;(IPC1-7):E02D3/12 |
主分类号 |
E02D3/12 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|