摘要 |
PROBLEM TO BE SOLVED: To improve the productive efficiency and transport efficiency of a house unit constituting a unit house when the unit house is built. SOLUTION: The unit house A is constrained only by the unit size of a transport means singly and divided without being restricted by partitions and columns 15, and production units 16a-16g are set. At corner sections in the production units, temporary materials 17 are arranged at sites, where there is no members connecting a ceiling section 18 and a floor section 19, and both ceiling section 18 and floor section 19 are connected and the house units 16a-16g are manufactured. The house units 16a-16g are installed at plots, where the house A is built, the adjacent house units are connected mutually, and the house A is constructed by removing the temporary materials 17.
|