摘要 |
The present invention discloses how once the building has been re-found with control piles, the following proceeds: 1.- over each control pile, from the once placed in building foundation most unleveled part, are placed hydraulic cylinders, with double metallic bridge, with screws and nuts which give continuity to anchoraged existing screws. 2.- under dies, from building foundation less unleveled part, excavations or diggings are performed in calculated way to remove supporting area to foundation flagstone. 3.- it is applied, in simultaneous and gradual way a hydraulic charge to piles having hydraulic cylinders, to cause a controlled descent, through control devices, and in gradual way, recover verticality in inclined buildings.
|