发明名称 Shrouded bridge and its construction process
摘要 The bridge is designed so that the loads exerted by each pylon 2 on its foundation 3 have no horizontal element and so that there is no reaction between the deck 1 and the supports 5. Moreover, each pylon may be displaced horizontally on its foundation without disassociating it from the deck. To construct such a bridge in place of an old bridge to be destroyed, the new bridge is built at the side of the old bridge. Traffic is diverted, the old bridge is demolished, the foundations are extended if necessary and then the new bridge is moved into its final position. The invention is also applicable for compensating for future variations in the length of the deck. <IMAGE>
申请公布号 FR2619839(A1) 申请公布日期 1989.03.03
申请号 FR19870011888 申请日期 1987.08.25
申请人 MULLER INTERNATIONAL JEAN 发明人 JEAN MULLER
分类号 E01D19/14;E01D22/00 主分类号 E01D19/14