摘要 |
PURPOSE:To shorten the working period as well as reduce the construction cost for reinforced banking by a method in which an exterior member is erected, a strip member is connected to the exterior member and laid horizontally, and then banking and tamping are conducted. CONSTITUTION:An exterior member 1 is erected on the ground to form an exterior wall 2, banking 4 is conducted up to the level of the lowermost fitting metal 5 and tamped horizontally, and then a strip member 3 is connected to the lowermost fitting metal 5. And so, the strip member 3 is laid horizontally on the banking. The connection and laying of the strip member 3 and the moving and tamping of the banking are orderly repeated upwardly for every interval of the fitting metals 5 in order to construct a reinforced banking. |