发明名称 Concrete post foundation hole prodn. - involves lowering pipe into ground using vibrator and core is removed using differential air pressure
摘要 <p>The process is for the positioning of concrete posts or similar construction elements, in the ground. A hole is dug in the ground, corresponding to the cross section of the post. A pipe (16), open at the bottom, and having the desired cross section, is pressed into the ground by a vibrator, placed onto its top end. A pressure differential, relative to atmospheric pressure, is produced in an end section of the pipe, to keep the soil within the pipe. The pipe is then retracted while the pressure is maintained within it. Compressed air is introduced at the lower end of the pipe, and the supply is maintained, while the pipe is withdrawn. The top pipe end is sealed air-tight after insertion.</p>
申请公布号 DE2851619(A1) 申请公布日期 1980.06.04
申请号 DE19782851619 申请日期 1978.11.27
申请人 FRITZ MANN GMBH & CO 发明人
分类号 E02D5/38;(IPC1-7):02D17/142;02D5/38 主分类号 E02D5/38
代理机构 代理人
主权项
地址