摘要 |
PROBLEM TO BE SOLVED: To provide a work truck which facilitates assembly of timbering and spray of concrete in construction of a large sectional tunnel. SOLUTION: The work truck C is comprised of a base stand 4 movable in the tunnel, guide rails G<SB>1</SB>, G<SB>2</SB>, G<SB>3</SB>, G<SB>4</SB>borne by the base stand 4, timbering assembling means 5L, 5R movably borne by the left and right guide rails G<SB>1</SB>, G<SB>3</SB>, respectively, and concrete spraying means 6L, 6R movably borne by the left and right guide rails G<SB>2</SB>, G<SB>4</SB>, respectively. The guide rails G<SB>1</SB>, G<SB>2</SB>, G<SB>3</SB>, G<SB>4</SB>are arranged along tunnel inner surfaces 1L, 1R, and therefore even if the tunnel has a large cross section, assembly of the timbering 2 and spray of the concrete are achieved along the entire inner surface of the tunnel. COPYRIGHT: (C)2005,JPO&NCIPI
|