<p>PROBLEM TO BE SOLVED: To provide the construction method for a submarine buried structure in which a pipe can be protected excellently and construction work is facilitated when a seabottom ground surface is excavated and a pipe is laid. SOLUTION: An excavated ditch 20 is built by digging-down from a seabottom ground surface 8, crushed stones or the like are charged onto the bottom of the excavated ditch and a foundation bearing layer 21 is constructed, and a bearing member 27 is arranged onto the layer 21 and a pipe P is laid. Rubbles are charged to the underside and side faces of the pipe P and a rubble layer in fixed thickness is built, an asphalt mixture 25 is placed on the rubble layer and a bearing layer 22 is constructed, an upper covering layer 26 is executed onto the layer 22 and a top-face protective material 28 is installed, and bearing and protection to a pipeline can be conducted.</p> |
申请公布号 |
JP2001032301(A) |
申请公布日期 |
2001.02.06 |
申请号 |
JP19990204141 |
申请日期 |
1999.07.19 |
申请人 |
WORLD ENGINEERING KK;NIPPON ROAD CO LTD:THE;TAISEI ROTEC CORP;NIPPON KAIJO KOJI KK |
发明人 |
WAGI TAKATSU;ORIGASA MASAMI;NONODA MITSURU;ITO TAKAHIKO;MATSUZAKI KATSUO;NAKANO HIROSHI |
分类号 |
E02D29/073;F16L1/12;(IPC1-7):E02D29/073 |