发明名称 FORMATION WORK OF CEMENT MORTAR PILE IN GROUND WITH WOODEN PILE
摘要 PURPOSE:To concurrently perform the removal of a wooden pile and the formation of cement-mortar pile by a method in which a casing with an existing wooden pile is pulled up from ground and cement mortar is poured from an injecting tube attached to the casing into the ground. CONSTITUTION:A casing 1 is turned, excavating water is jetted from a nozzle 2, and the casing 1 is penetrated to above an existing wooden pile 10a. The turning of the casing 1 with the pile 10a and the supply of excavating water are stopped, and while supplying cement mortar through an injecting tube 6, the casing 1 is pulled up to the ground's surface. The removal of the existing wooden pile 10 and the formation of the cement mortar pile can thus be performed concurrently.
申请公布号 JPS62202117(A) 申请公布日期 1987.09.05
申请号 JP19860044896 申请日期 1986.02.28
申请人 TOTSUKI KOGYO KK 发明人 OCHI NAGATOMO
分类号 E02D5/38;E02D7/00 主分类号 E02D5/38