发明名称 Data center physical infrastructure threshold analysis
摘要 Analyzing one or more physical infrastructure elements of a data center by generating a plurality of outputs from a stochastic process for a set of inputs to the stochastic process. The inputs comprise one or more inputs of certainty and one or more inputs of uncertainty. A statistical output analysis of the outputs is utilized to generate one or more threshold reaching projections for each of the physical infrastructure elements of the data center.
申请公布号 US9454449(B2) 申请公布日期 2016.09.27
申请号 US201314020251 申请日期 2013.09.06
申请人 Globalfoundries Inc. 发明人 Bagchi Sugato;Ghosh Soumyadip;Ramos Stacey
分类号 G06F17/50;G06F11/30;G06Q10/06 主分类号 G06F17/50
代理机构 Heslin Rothenberg Farley & Mesiti P.C. 代理人 Heslin Rothenberg Farley & Mesiti P.C.
主权项 1. A method for analyzing one or more physical infrastructure elements of a data center, said method performed by execution of computer-readable program code by at least one processor of at least one computer system, said method comprising: generating, using at least one of the processors, a plurality of outputs from a stochastic process for a set of inputs to said stochastic process, wherein said stochastic process includes a plurality of evaluations of a deterministic model, said set of inputs comprising one or more inputs of certainty and one or more random variables having a probability distribution, and wherein for an evaluation of said plurality of evaluations of a deterministic model a random number determined from a probability distribution of said one or more random variables having a probability distribution is input into said deterministic model; performing, using at least one of the processors, a statistical output analysis of said outputs; and utilizing, using at least one of the processors, said statistical output analysis to generate one or more threshold reaching projections for each of said one or more physical infrastructure elements of said data center, wherein each of said one or more physical infrastructure elements has a threshold capacity, and wherein said inputs of certainty comprise a threshold capacity of each of said one or more physical infrastructure elements, wherein each of said one or more physical infrastructure elements is an infrastructure element selected from the group consisting of power density, a raised floor, a UPS, utility power, a generator, a chiller, a CRAC, and a layout efficiency.
地址 Grand Cayman KY