<p><P>PROBLEM TO BE SOLVED: To reduce a manufacturing cost of a temporary elevator installed inside a building, and promptly remove the elevator from the floor where the construction has progressed. <P>SOLUTION: In a method for installing the elevator 10, the elevator 10 installed in a high-rise building 1 under construction is lifted and relocated to a higher floor side in a state that a carrier 20, a rail 30 that guides the ascent and descent of the carrier 20, and a frame 40 to which the rail 30 is connected and which extends along a hoistway of the carrier 20 are integrated. The elevator 10 in a state that the carrier 20, the rail 30 and the frame 40 are assembled beforehand is lifted above the high-rise building 1 under construction, and lowered through an opening 7 provided to a slab 6 of each floor so as to be installed inside the high-rise building 1. <P>COPYRIGHT: (C)2013,JPO&INPIT</p> |