发明名称 Steam turbine bucket tenon restoration through solid state bonding process
摘要 Tenons can be installed at the ends of turbine blades by applying a solid state bonding procedure such as a friction welding technique to join the tenons to the turbine blades. The tenons can be employed to assemble the turbine blades to one or more covers for the turbine blades. The tenons can be installed in connection with the restoration of tenons for turbine buckets in steam turbines and in connection with the renovation of rotor assemblies that include turbine blades secured to a common disk, tenons located at one end of respective turbine blades and one or more covers secured to the turbine blades by means of the tenons. In instances in which tenon remnants are present at the ends of the turbine blades, tenon enlargement elements can be joined to the tenon remnants by the solid state bonding procedure. The tenon installations can be carried out in situ.
申请公布号 US9163511(B2) 申请公布日期 2015.10.20
申请号 US201213719557 申请日期 2012.12.19
申请人 GENERAL ELECTRIC COMPANY 发明人 Wojciechowski Marek;Żarnik Marciej Jan
分类号 F01D5/00;F01D5/14;B23P6/00 主分类号 F01D5/00
代理机构 Cooper Legal Group, LLC 代理人 Cooper Legal Group, LLC
主权项 1. A method of installing at least one respective tenon at each of one or more turbine blades including: providing one or more turbine blades at which at least one respective tenon is to be installed, each turbine blade including a first end that is configured to be secured to a turbine disk and a second end that is located substantially opposite the first end of the turbine blade; orienting the second end of each turbine blade at which at least one respective tenon is to be installed in an attitude that is accommodative to the installation of the at least one respective tenon at the second end of each turbine blade; and installing the at least one respective tenon at the second end of each turbine blade at which the at least one respective tenon is to be installed by applying a solid state bonding procedure to join the at least one respective tenon to the second end of each turbine blade; wherein the second end of each turbine blade at which the at least one respective tenon is to be installed includes at least one tenon remnant identified for restoration and the step of installing the at least one respective tenon at the second end of each turbine blade at which the at least one respective tenon is to be installed by applying a solid state bonding procedure to join the at least one respective tenon to the second end of the turbine blade includes bonding a respective tenon enlargement element to each of the at least one tenon remnants identified for restoration.
地址 Schenectady NY US