发明名称 PROCESS OPTIMIZATION METHOD AND SYSTEM FOR A POWER PLANT
摘要 <p>A method and system are disclosed for optimizing load scheduling for a power plant having one or more power generator units. An exemplary method and corresponding system can involve detecting an event indicative of a need for adapting one or more constraints for an objective function used in load scheduling. On such detection, the objective function is analysed to determine adaptive constraint values for the one or more constraints for optimally solving the objective function. These adaptive constraint values can be used to solve the objective function and the solution of the objective function with the one or more adapted constraint values can be used to operate the one or more power generation units of the power plant.</p>
申请公布号 EP2519862(A1) 申请公布日期 2012.11.07
申请号 EP20100726200 申请日期 2010.05.13
申请人 ABB RESEARCH LTD. 发明人 SHANMUGAM, MOHAN, KUMAR;SUNDARAM, SENTHIL, KUMAR;SELVARAJ, GOPINATH;BHAT, SHRIKANT
分类号 G05B13/04;F02C9/42 主分类号 G05B13/04
代理机构 代理人
主权项
地址