摘要 |
PROBLEM TO BE SOLVED: To reduce breakage and damages to a concrete foundation resulting from ground deformation, while securing water cut-off performance. SOLUTION: Adjacent foundation slabs 20 are connected to each other with concrete connecting bodies 22 smaller in rigidity than these foundation slabs 20. The joint space 28 between the adjacent foundation slabs 20 are embedded with the concrete connecting bodies 22, inhibiting the intrusion of water from the ground 18 on the support surface 20A of the concrete connecting bodies. COPYRIGHT: (C)2011,JPO&INPIT |