摘要 |
PROBLEM TO BE SOLVED: To provide a rope hooking structure for a crane optimum for shift control. SOLUTION: A pair of two ropes 78, 74 and 73, 77 drawn out from a drum 16 are laid on a rope winding virtual surface supposed on an end part in a lateral direction of a hanging unit 8 such that the respective ropes form a triangle between the hanging unit 8 and the trolley 6 and hypotenuses x4, x8 and x3, x7 are opposed to each other. Further, a pair of rope operation plates is turnably pivotally supported on the trolley 6, and a pair of two ropes 78, 74 and 73, 77 arranged on the rope winding virtual surface supposed on the end part in the lateral direction of the hanging unit 8 are attached to front end parts of the respective rope operation plates 124, 125. Further, the respective rope operation plates 124, 125 are turned in an opposite direction to each other by shift control devices 130, 140. COPYRIGHT: (C)2011,JPO&INPIT |