CONSTRUCTION METHOD FOR UNDERGROUND WALL USING TWO ROWS PILE |
摘要 |
PURPOSE: A construction method for an underground wall using two-row piles is provided to perform deep excavation and facilitate excavation works as there is not a reinforcement structure within an excavation area. CONSTITUTION: A construction method for an underground wall using two-row piles comprises the followings. An underground wall(10) which is reinforced by an inner reinforcing bar along the interface of an excavation area(1) is formed. The two-row pile(200) is inserted into the outside of the underground wall at constant intervals. The underground wall and the two-row pile are mutually connected by a connection member(300) to move the underground wall and the two-row pile together. An excavation area is excavated. |
申请公布号 |
KR20090116159(A) |
申请公布日期 |
2009.11.11 |
申请号 |
KR20080041910 |
申请日期 |
2008.05.06 |
申请人 |
KOLON CONSTRUCTION CO., LTD. |
发明人 |
SON, SUNG GON;SIM, JAE UK |
分类号 |
E02D29/045;E21D9/04 |
主分类号 |
E02D29/045 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|