发明名称 METHOD OF SHORTENING CURING PERIOD OF ASPHALT CONCRETE LAYER
摘要 PROBLEM TO BE SOLVED: To provide a method of shortening a curing period of an asphalt concrete layer and shortening a construction period, in construction of an elastic pavement consisting of the asphalt concrete layer and a pavement layer placed on the same, the method having been conventionally carried out by placing the asphalt concrete layer, leaving the same in the natural environment for two weeks or more as a curing period to degrade a surface of the asphalt concrete layer, and placing the pavement layer on the degraded surface. SOLUTION: The method of shortening the asphalt concrete layer curing period is carried out by brushing the surface of the asphalt concrete layer placed on a substrate, in construction of the pavement. According to the method a sweeper on which a plastic or wire brush is mounted is operated to travel on the asphalt concrete layer, and to wash the surface by spraying sand or water on the same as needed. COPYRIGHT: (C)2006,JPO&NCIPI
申请公布号 JP2006097294(A) 申请公布日期 2006.04.13
申请号 JP20040283383 申请日期 2004.09.29
申请人 TOYO SPORTS SHISETSU KK 发明人 SATO TAKAYUKI;SATO OKIMASA;ISHIBASHI YOSHIHARU;SHIBAHARA TOSHIHARU
分类号 E01C3/00;E01C13/00 主分类号 E01C3/00
代理机构 代理人
主权项
地址