发明名称 COMPLETION METHOD FOR POURING OF MOLTEN STEEL IN TUNDISH
摘要 PROBLEM TO BE SOLVED: To provide a method capable of pouring nearly all of molten steel in the tundish without any operator's operation at the casting end stage completing the pouring of the molten steel from a ladle into the tundish and also minimizing the flow-out of slag in a tundish into a mold. SOLUTION: When continuous casting is performed by pouring the molten steel 12 into the mold 2 through a sliding nozzle 3 from the tundish 1, since completing the pouring of the molten steel from the ladle into the tundish, the opening degree of the sliding nozzle is watched and it is determined that the time point when the variation speed of the opening degree of the sliding nozzle is rapidly risen up, as the time point for completing the pouring of the molten steel from the tundish, and the sliding nozzle is automatically closed. At this time, it is desirable to close at the time point when the variation speed of the opening degree of the sliding nozzle becomes≥5 mm/sec. COPYRIGHT: (C)2005,JPO&NCIPI
申请公布号 JP2005262222(A) 申请公布日期 2005.09.29
申请号 JP20040074040 申请日期 2004.03.16
申请人 JFE STEEL KK 发明人 IDO HIROHARU;KAMEDA SUMIHIRO;MIYAMOTO AKIRA
分类号 B22D11/10;B22D11/16;B22D37/00;B22D41/50;B22D43/00;(IPC1-7):B22D11/10 主分类号 B22D11/10
代理机构 代理人
主权项
地址