发明名称 |
CONSTRUCTION METHOD FOR PRESS-IN PILE |
摘要 |
PROBLEM TO BE SOLVED: To provide a construction method for driving a pile under a basic skeleton for carrying out base isolation repair work of the existing building. SOLUTION: Press-in load slightly more than design yield load required for the pile is mounted on a pile body to advance press-in. A creep settlement speed of the pile body mounting press-in load thereon is measured, and the pile body is driven up to a depth not more than control value for the creep settlement speed set in advance to complete. COPYRIGHT: (C)2005,JPO&NCIPI
|
申请公布号 |
JP2005023562(A) |
申请公布日期 |
2005.01.27 |
申请号 |
JP20030187784 |
申请日期 |
2003.06.30 |
申请人 |
TAKENAKA KOMUTEN CO LTD |
发明人 |
YAMADA TAKESHI;AOKI MASAMICHI;SATO EIJI;YAMASHITA KIYOSHI;IWATA MASAYUKI;MIZUNO AKIRA |
分类号 |
E02D27/48;E02D7/20;(IPC1-7):E02D7/20 |
主分类号 |
E02D27/48 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|