发明名称 CONSTRUCTION METHOD FOR PRESS-IN PILE
摘要 PROBLEM TO BE SOLVED: To provide a construction method for driving a pile under a basic skeleton for carrying out base isolation repair work of the existing building. SOLUTION: Press-in load slightly more than design yield load required for the pile is mounted on a pile body to advance press-in. A creep settlement speed of the pile body mounting press-in load thereon is measured, and the pile body is driven up to a depth not more than control value for the creep settlement speed set in advance to complete. COPYRIGHT: (C)2005,JPO&NCIPI
申请公布号 JP2005023562(A) 申请公布日期 2005.01.27
申请号 JP20030187784 申请日期 2003.06.30
申请人 TAKENAKA KOMUTEN CO LTD 发明人 YAMADA TAKESHI;AOKI MASAMICHI;SATO EIJI;YAMASHITA KIYOSHI;IWATA MASAYUKI;MIZUNO AKIRA
分类号 E02D27/48;E02D7/20;(IPC1-7):E02D7/20 主分类号 E02D27/48