发明名称 ERECTION METHOD OF MULTI-SPAN CONTINUOUS PREFLEX COMPOSITE BRIDGE OR RE-PRESTRESSED PREFLEX COMPOSITE BRIDGE
摘要 PURPOSE: An erection method of a multi-span continuous preflex composite bridge of a re-prestressed preflex composite bridge is provided to exactly transmit reaction of upper live load to the center of a pier and improve the appearance of the lower part of the bridge. CONSTITUTION: A preflex composite beam(1) or a re-prestressed preflex composite beam formed by composition of a steel I-shaped girder(2) and reinforced concrete(3) or steel strand for prestressed concrete is each manufactured on the ground. Each beam is independently erected on each span of the multi-span bridge as a simple beam structure and mechanism subsystem. The steel I-shaped girder of each span beam is combined completely continuously to change the simple beam structure and mechanism subsystem into a continuous structure and mechanism subsystem. One bridge seat apparatus(6) is installed to each continuous combining portion of each span beam.
申请公布号 KR20030075455(A) 申请公布日期 2003.09.26
申请号 KR20020014693 申请日期 2002.03.19
申请人 DONG YANG PSC;DONGYANG CONSTRUCTION CO., LTD. 发明人 KIM, WON GEUN;KWON, O GEUN;LEE, MU IL;YOON, SUK HYEON
分类号 E01D2/02;(IPC1-7):E01D2/02 主分类号 E01D2/02
代理机构 代理人
主权项
地址