PROBLEM TO BE SOLVED: To provide a shaft connecting method for connecting a shaft to a horizontal tunnel in a short period of time, and to provide a shaft connecting structure. SOLUTION: According to the shaft connecting method, a starting shaft 5 and an arrival shaft 7 are constructed in the ground 3, and the shaft 9 is constructed at a midpoint between the starting shaft 5 and the arrival shaft 7. After the construction of the shaft 9, soil mortar 11 is filled in the ground from a lower end of the shaft, and then a shield tunnel 15 is constructed from the side of the starting shaft 5 by a shield machine 13. At this time, the shield machine 13 cuts part of the soil mortar 11. Then, the shield tunnel 15 and the shaft 9 are connected together by man-power, etc. COPYRIGHT: (C)2003,JPO
|