发明名称 TUNNEL EXCAVATING CONSTRUCTION METHOD AND TUNNEL LINER USED THEREFOR
摘要 PROBLEM TO BE SOLVED: To provide a tunnel excavating construction method and a tunnel liner used in this construction method of excavating with a tunnel boring machine using the tunnel liner lightweight and low in cost compared with segments and making the degree of support reinforcement changeable according to the state of the natural ground in a tunnel in a mountain. SOLUTION: Each constituent member of a prefabricated tunnel liner 10 composed of a plurality of main girder rings 1 using shape steel, and a deck plate 2 provided bridging between a plurality of main girder rings, is manufactured outside of a tunnel T. Each constituent member in a bulk state or in a unit built-up state is carried into an excavation site in the tunnel T reinforced or omitted according to the state of the natural ground to build up the prefabricated tunnel liner 10, and a tunnel boring machine M is put in excavating action.
申请公布号 JPH11311096(A) 申请公布日期 1999.11.09
申请号 JP19980118558 申请日期 1998.04.28
申请人 KAJIMA CORP;NIPPON STEEL CORP 发明人 NISHIOKA KAZUNORI;MATSUDA MASAKAZU;IWATA MITSUISA;YOKOO ATSUSHI;SASAKI MICHIO;HATADA MINORU
分类号 E21D9/10;E21D11/14;(IPC1-7):E21D11/14 主分类号 E21D9/10
代理机构 代理人
主权项
地址