发明名称 METHOD OF PIPING DRAWING-IN CONSTRUCTION
摘要 <p>PURPOSE:To reduce the quantity of a drive ditch excavated extremely while simplifying a landslide protection wall, to charge and connect pipes in a small number of connecting sections, and to simplify the excavation operation of the drive ditch and the charging operation of the pipes while largely shortening the connection time of the pipes. CONSTITUTION:Fluidized soil 7 using excavated soil is placed on the floor face of a drive ditch 2. A smooth surface is formed in the floor face of the drive ditch by hardening the fluidized soil 7. The surface of the fluidized soil 7 of the drive ditch 2 is slid while successively welding pipes 1 charged at the predetermined fixed place 3 of the drive ditch, and drawn into the drive ditch 2.</p>
申请公布号 JPH07310333(A) 申请公布日期 1995.11.28
申请号 JP19940128011 申请日期 1994.05.19
申请人 JAPAN STEEL & TUBE CONSTR CO LTD 发明人 OTA KAZUYUKI;AIZAWA YOSHITERU;MIZUNO KAZUHIRO;MATSUO ATSUSHI;HARA NAOKI
分类号 E02F5/10;F16L1/024;(IPC1-7):E02F5/10 主分类号 E02F5/10