发明名称 Method for installation of heavyweight foundation system for off-shore wind energy plant, involves countersinking base body into seabed, and temporarily preloading foundation by ballast bodies engaged at foundation in limited manner
摘要 <p>The method involves transporting a heavyweight foundation (10) and a vertical shaft (14) for supporting a tower of a wind energy plant (WEA) by a floating body (22) as a unit to a work place. The unit is lowered on a seabed at the work place. A bottom of a setting surface is fluidized by pressure water for a concrete annular base body (12). The base body is countersinked into the seabed by simultaneous displacement of fluidized bottom material to a side due to weight load of the base body. The foundation is temporarily preloaded by ballast bodies engaged at the foundation in a limited manner. The shaft is designed as a latticed mast. The heavyweight foundation is a shallow foundation and a pile foundation.</p>
申请公布号 DE102012016692(A1) 申请公布日期 2014.02.27
申请号 DE20121016692 申请日期 2012.08.24
申请人 WERNER MOEBIUS ENGINEERING GMBH 发明人 MOEBIUS, WERNER
分类号 E02D27/52 主分类号 E02D27/52
代理机构 代理人
主权项
地址