发明名称 |
SLAB TOP-DOWN METHOD OF UNDERGROUND CONSTRUCTION |
摘要 |
PURPOSE: A reverse direction construction method of an underground structure is provided to reduce production times and costs by the formation of a slab on concrete. CONSTITUTION: A reverse direction construction method of an underground structure comprises following steps. An underground continuous wall is formed on an underground position where an underground outer wall will be formed, so that an underground outer line may be formed(S10). Multiple center piles are built in the surface divided by the underground continuous wall, so that a base frame of a post is formed(S20). Two or more slabs forming the bottom surface of each under layer are laminated to move along multiple center piles(S30). |
申请公布号 |
KR20100100165(A) |
申请公布日期 |
2010.09.15 |
申请号 |
KR20090018889 |
申请日期 |
2009.03.05 |
申请人 |
LEE, SAI HWAN;LEE, YE REE |
发明人 |
LEE, SAI HWAN;LEE, YE REE |
分类号 |
E02D29/045;E21D9/04 |
主分类号 |
E02D29/045 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|