摘要 |
<p><P>PROBLEM TO BE SOLVED: To provide an air conditioning system carrying out equalization of electric power consumption and reducing facility costs and operation costs by cutting a cooling (heating) load during the peak of the summer (winter) season, and eliminating double cooling or heating such as carrying out precooling (preheating). <P>SOLUTION: In the air conditioning system, a plurality of air conditioners is installed in an air conditioning space, heat source water is heat-exchanged by a heat exchanger in a main cooling/heating facility, and it is recovered and circulated by a return pipe. One part or all of the heat source water is additionally cooled or heated by a supplementary cooling facility or a supplementary heating facility other than the main cooling facility or the main heating facility in response to operating states of the main cooling facility or the main heating facility, and it is supplied to an outward pipe or the return pipe. <P>COPYRIGHT: (C)2009,JPO&INPIT</p> |