摘要 |
PROBLEM TO BE SOLVED: To solve a problem wherein a size, a material amount and a manufacturing cost of the whole system increase, and further a problem wherein a pressure loss increases in the system, by lengthening and enlarging a connection pipe and by adopting a plurality of pressure containers, because the pressure containers are required to be manufactured and installed respectively in an IHX and a gas turbine system, by installing the IHX vertically, and because the pipe is required to be laid around to connect fellow devices. SOLUTION: The size and the facility material amount of the whole system are remarkably reduced and the manufacturing cost thereof is remarkably reduced, by integrating the devices constituting the system and by simplifying system constitution. A heat efficiency is enhanced also by simplifying the system constitution to reduce a heat loss and the pressure loss. COPYRIGHT: (C)2009,JPO&INPIT
|