发明名称 |
METHOD OF PREPARING TO OPERATION AND INSTALLATION OF BLAST FURNACE AIR TUYERE |
摘要 |
FIELD: metallurgy. ^ SUBSTANCE: method includes mechanical removal of an oxidated layer off the surface of an inside cartridge from the side of a blow channel and muzzle part of the tuyer with thermal treated aluminium containing gas thermal coat. Then an aluminium containing coating is applied on the outer surface of the muzzle part of the tuyer. Then the tuyer is installed into a blast furnace in not earlier than twenty four hours after coating application. ^ EFFECT: invention reduces heat losses through a tuyer and increases its burn out resistance. ^ 2 cl, 1 tbl, 1 ex |
申请公布号 |
RU2327742(C2) |
申请公布日期 |
2008.06.27 |
申请号 |
RU20060115720 |
申请日期 |
2006.05.06 |
申请人 |
OTKRYTOE AKTSIONERNOE OBSHCHESTVO "SEVERSTAL'" (OAO "SEVERSTAL'") |
发明人 |
LOGINOV VALERIJ NIKOLAEVICH;SUKHANOV MIKHAIL JUR'EVICH;KARIMOV MIKHAIL MURTAZAKULOVICH;TITLJANOV ALEKSANDR EVGRAFOVICH;RADJUK ALEKSANDR GERMANOVICH |
分类号 |
C21B7/16 |
主分类号 |
C21B7/16 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|