发明名称 TEMPORARY STRUCTURE AND PRECAST CONCRETE BEAM OF PYLON SETTING METHOD USING THE BRACKET
摘要 A temporary construction bracket installation structure and a method for installing a tower PC(Precast Concrete) cross beam of a cable stayed bridge using a temporary construction bracket are provided to confirm that the horizontal beams of the tower are easily constructed, to reduce construction time, and to set the position of the horizontal beams easily using horizontal supporters of temporary construction brackets. A temporary construction bracket installation structure comprises temporary construction brackets(100), prestressing steel rods(210), and sheath pipes(220). The temporary construction brackets include vertical and horizontal supporters, and inclined supporters for connecting the vertical and horizontal supporters. The prestressing steel rods fix a lower structure contacted with the vertical supporters. The sheath pipes are buried in each part through which the prestressing steel rods pass. Fixing bolts(230) are fixed at the lower structure.
申请公布号 KR100820299(B1) 申请公布日期 2008.04.08
申请号 KR20070047064 申请日期 2007.05.15
申请人 SAMSUNG CORPORATION 发明人 KIM, HWA SOO;SON, YU SUK;PARK, HAE IL;YOO, JAE KUN;KIM, YOUNG WOO;KIM, CHANG HYUN
分类号 E01D19/02;E01D21/00 主分类号 E01D19/02
代理机构 代理人
主权项
地址