发明名称 |
WORK EXECUTION METHOD FOR LARGE SECTION TUNNEL AND DEFORMED SECTION SHIELD BORING MACHINE |
摘要 |
PROBLEM TO BE SOLVED: To provide a construction method for a large section tunnel having a shallow overburden and a deformed section shield boring machine. SOLUTION: A rectangular excavation trench 3 in section view is formed in the ground to back-fill the upper part of a box body to construct a row of box bodies 23 while adjacently installing the box body 2, a row of propulsive pipes 73 are constructed by installing the propulsive pipe 7 under the box body 2 while fitting an projected stripe 71 expanded in the direction of a tunnel axis on the upper surface of an upper floor slab 72 of the propulsive pipe 7 in a groove stripe 22 notched in the direction of the tunnel axis on the lower surface of the bottom slab of the box body 2, excavation is carried out between a plurality of rows of box bodies 23 constructed in approximately parallel with each other at an interval 6 and a row of propulsive pipes 73, and while the large section tunnel 4 is constructed while utilizing a row of box bodies 23 and a row of propulsive pipes 73 as an earth retaining supporting member. A row of box bodies 23 are precedently constructed, and an upper stage box body 24 can be installed while forming the excavation trench 3 thereon. When the excavation trench 3 is formed, an open shield machine 11 or a deformed section shield machine 12 is used. COPYRIGHT: (C)2005,JPO&NCIPI |
申请公布号 |
JP2004316126(A) |
申请公布日期 |
2004.11.11 |
申请号 |
JP20030108373 |
申请日期 |
2003.04.11 |
申请人 |
TAISEI CORP;ISHIKAWAJIMA HARIMA HEAVY IND CO LTD;ISHIKAWAJIMA CONSTR MATERIALS CO LTD |
发明人 |
KANEKO KENICHI;OTA MITSUHIKO;YUGUCHI MASAKI;OHATA YUTAKA;UEDA KENRO;KADOTA KATSUMI;ITO HIROYUKI;SAKUMA YUJI;HASHIMOTO HIROHIDE;WAKABAYASHI MASANORI |
分类号 |
E21D9/06;E02D29/05;(IPC1-7):E02D29/05 |
主分类号 |
E21D9/06 |
代理机构 |
|
代理人 |
|
主权项 |
|
地址 |
|