发明名称 Procedure for erecting of tower for wind power plant from prefabricated elements, involves lifting and mounting elements by assembly unit which is moved by walking support
摘要 The procedure for the erecting of a tower from prefabricated elements entails lifting and mounting at least a part of the elements (3,5) by an assembly unit (4) progressively movable on the tower. The assembly unit is moved by a walking support which is symmetrical to the center axis of the already mounted elements. The assembly unit is moved by vertically movable arms (19) connected via mounting elements (21) to the prefabricated elements. An Independent claim is included for a device for the erecting of towers from prefabricated elements using an assembly unit with a walking support.
申请公布号 DE10212305(A1) 申请公布日期 2003.10.02
申请号 DE2002112305 申请日期 2002.03.20
申请人 WALTER BAU-AG 发明人 WALLENBERGER, ALOIS;GROSS, HANS-WALTER
分类号 E04H12/34;F03D1/00 主分类号 E04H12/34
代理机构 代理人