发明名称 |
Start-Up Control Device and Start-Up Control Method for Power Plant |
摘要 |
To provide a start-up control device and a start-up control method for a power plant capable of changing the start-up completion estimated time to a desired time simply and safely while starting the power plant. The start-up control device includes an equipment state quantity acquisition unit acquiring an equipment state quantity of the power plant, a start-up schedule calculation unit calculating a current start-up schedule based on the equipment state quantity and a first thermal stress limiting value and calculating a start-up schedule changing plan based on the equipment state quantity and a second thermal stress limiting value, an equipment operation amount calculation unit calculating an equipment operation amount of the power plant based on the current start-up schedule, a screen display unit displaying respective start-up completion estimated times of the current start-up schedule and the start-up schedule changing plan, and an instruction input unit instructing the start-up schedule calculation unit to perform switching from the current start-up schedule to the start-up schedule changing plan. |
申请公布号 |
US2017023933(A1) |
申请公布日期 |
2017.01.26 |
申请号 |
US201615215915 |
申请日期 |
2016.07.21 |
申请人 |
Mitsubishi Hitachi Power Systems, Ltd. |
发明人 |
KAWATA Miyuki;YOSHIDA Yasuhiro;YOSHIDA Takuya;YASHIKI Tatsuro;KIM Eunkyeong;YAMANAKA Kazunori;IYANAGA Norihiro;YAMASHITA Atsushi |
分类号 |
G05B19/418;F01K13/02;G05F1/66 |
主分类号 |
G05B19/418 |
代理机构 |
|
代理人 |
|
主权项 |
1. A start-up control device for a power plant including a steam turbine, comprising:
an equipment state quantity acquisition unit acquiring an equipment state quantity of the power plant; a start-up schedule calculation unit calculating a current start-up schedule based on the equipment state quantity and a predetermined first constraint condition and calculating a start-up schedule changing plan based on the equipment state quantity and a predetermined second constraint condition; an equipment operation amount calculation unit calculating an equipment operation amount of the power plant based on the current start-up schedule; a screen display unit displaying start-up completion estimated times with respect to the current start-up schedule and the start-up schedule changing plan respectively; and an instruction input unit outputting an instruction for switching from the current start-up schedule to the start-up schedule changing plan to the start-up schedule calculation unit in accordance with an input operation by an operator. |
地址 |
Nishi-ku JP |