Method of reducing or eliminating dynamic effect on permanent lining of mine tunnel - involves installation of cushioning layer simultaneously with drainage and sealing processes
摘要
A method of reducing or eliminating the dynamic effect on the permanent lining of a mine roadway or other tunnel by the installation of a cushioning or shock absorbing flat sheet. Drainage, leakage detection and sealing are carried out at the same time. The tunnel (2) is protected from shock waves (3) by rock nails or anchors (4) driven into the rock face (1) radially followed by a sprayed concrete liner (5) and the cushioning layer (6). USE/ADVANTAGE - The cushioning layer is not primarily for sealing or drainage through it may be combined with these processes.
申请公布号
DE4133577(A1)
申请公布日期
1992.06.17
申请号
DE19914133577
申请日期
1991.10.10
申请人
GBM GESELLSCHAFT FUER BAUGEOLOGIE UND -MESSTECHNIK MBH BERATUNGEN-UNTERSUCHUNGEN, 7505 ETTLINGEN, DE